St Johns C of E Primary School (2)
Project Name: St Johns C of E Primary School
Project Description: Renewal of 2no Heating Boilers
Location: Filmer Road, Fulham, London, SW6 6AS
Client: St Johns C of E Primary School
Project Manager: Westminster Diocese
Contract Duration: 6 Weeks
Value: £120,000.00
This project was to renew 2no heating boilers in the plant room and replace the existing pipework.
Spire carried out the following:
Provide access scaffolding.
Isolate and drain the existing system.
Cut out and remove galvanised steel pipework.
Supply and install thermostatic blending valves.
Clean cold water storage tank.
Supply and install MAG filter.
Complete all builders works, including making good, core holes, and decorations.