St Johns C of E Primary School (3)
Project Name: St Johns C of E Primary School
Project Description: Renewal of domestic hot water pipes
Location: Filmer Road, Fulham, London, SW6 6AS
Client: London Diocesan Board for Schools
Project Manager: Ian Fraser Associates
Contract Duration: 6 Weeks
Value: £138,000.00
This project involved the replacement of the galvanised steel pipework with copper.
Spire carried out the following:
Removal of existing steel pipework.
Installation of new copper pipework.
Renewal of thermostatic blending valves.
Clean cold water storage tank.
Insulate all pipework.
Decorations.